Project began onshore in 2017 and started offshore construction in Apr 2018. By May 2019, 50 of the 102 jackets supporting the turbine structures had been piled through c 35m of water. The installation covers c 165 km2 and was fully commissioned in Jul 2020. Operations are controlled from its new Hamilton Docks base at Lowestoft.